Function Task

14,000,000 Leading Edge Experts on the ideXlab platform

Scan Science and Technology

Contact Leading Edge Experts & Companies

Scan Science and Technology

Contact Leading Edge Experts & Companies

The Experts below are selected from a list of 243852 Experts worldwide ranked by ideXlab platform

Gerard T. Pittard - One of the best experts on this subject based on the ideXlab platform.

  • SEALING LARGE-DIAMETER CAST-IRON PIPE JOINTS UNDER LIVE CONDITIONS
    2005
    Co-Authors: Kiran M. Kothari, Gerard T. Pittard
    Abstract:

    Utilities in the U.S. operate over 75,000 km (47,000 miles) of old cast-iron pipes for gas distribution. The bell-and-spigot joints that connect pipe sections together tend to leak as these pipes age. Current repair practices are costly and highly disruptive. The objective of this program is to design, test and commercialize a robotic system capable of sealing multiple cast-iron bell and spigot joints from a single pipe entry point. The proposed system will perform repairs while the pipe remains in service by traveling through the pipe, cleaning each joint surface, and installing a stainless-steel sleeve lined with an epoxy-impregnated felt across the joint. This approach will save considerable time and labor, avoid traffic disruption, and eliminate any requirement to interrupt service to customers (which would result in enormous expense to utilities). Technical challenges include: (1) repair sleeves must compensate for diametric variation and eccentricity of old cast-iron pipes; (2) the assembly must travel long distances through pipes containing debris; (3) the pipe wall must be effectively cleaned in the immediate area of the joint to assure good bonding of the sleeve; and (4) an innovative bolt-on entry fitting is required to conduct repair operations on live mains. The development effort is divided into eleven Tasks. Task 1 (Program Management) and Task 2 (Establishment of Detailed Design Specifications) were completed previously. Task 3 (Design and Fabricate Ratcheting Stainless-Steel Repair Sleeves) has progressed to installing prototype sleeves in test cast-iron pipe segments. Efforts in the current quarter continued to be focused on Tasks 4-8. Highly valuable lessons were learned from field tests of the 4-inch gas pipe repair robot in cast-iron pipe at Public Service Electric & Gas. (These field tests were conducted and reported previously.) Several design issues were identified which need to be implemented in both the small- and large-diameter repair robots for cast-iron pipe to assure their commercial success. For Task 4 (Design, Fabricate and Test Patch Setting Robotic Train), previous problems with bladder design and elastomeric material expansion in the large mains were addressed. A new bladder based on a commercially available design was obtained and tested with success. Minor improvements were highlighted during patch-setting tests and are now being pursued. For Task 5 (Design and Fabricate Pipe-Wall Cleaning Robot Train with Pan/Zoom/Tilt Camera), the previous field tests showed clearly that, in mains with low gas velocities, it will be necessary to improve the system's capacity to remove debris from the immediate vicinity of the bell and spigot joints. Otherwise, material removed by the cleaning flails (the flails were found to be very effective in cleaning bell and spigot joints) falls directly to the low side of the pipe and accumulates in a pile. This accumulation can prevent the sleeve from achieving a leak-free repair. Similarly, it is also deemed necessary to design an assembly to capture existing servicetap coupons and allow their removal from the inside of the pipe. Task 6 (Design and Build Surface Control and Monitoring System) was previously completed with the control and computer display Functions being operated through LabVIEW. However, this must now be revisited to add control routines for the coupon catcher that will be added. This will most likely include a lift-off/place-on magnet translation Function. Task 7 (Design and Fabricate Large Diameter Live Access System) progressed to completing the detailed design for a bolt-on entry fitting for 12-inch diameter cast-iron pipe in the current quarter. The drilling assembly for cutting an access hole through the wall of the gas main was also designed, along with a plug assembly to allow removing all tools from the live main and setting a blind flange on the entry fitting prior to burial. These designs are described in detail in the report. Task 8 (System Integration and Laboratory Validation) continued with the development of the robot module inter-connects and of a master LabVIEW-based system display and control software

  • SEALING LARGE-DIAMETER CAST-IRON PIPE JOINTS UNDER LIVE CONDITIONS
    2005
    Co-Authors: Kiran M. Kothari, Gerard T. Pittard
    Abstract:

    Utilities in the U.S. operate over 75,000 km (47,000 miles) of old cast-iron pipes for gas distribution. The bell-and-spigot joints that connect pipe sections together tend to leak as these pipes age. Current repair practices are costly and highly disruptive. The objective of this program is to design, test and commercialize a robotic system capable of sealing multiple cast-iron bell and spigot joints from a single pipe entry point. The proposed system will perform repairs while the pipe remains in service by traveling through the pipe, cleaning each joint surface, and installing a stainless-steel sleeve lined with an epoxy-impregnated felt across the joint. This approach will save considerable time and labor, avoid traffic disruption, and eliminate any requirement to interrupt service to customers (which would result in enormous expense to utilities). Technical challenges include: (1) repair sleeves must compensate for diametric variation and eccentricity of cast-iron pipes; (2) the assembly must travel long distances through pipes containing debris; (3) the pipe wall must be effectively cleaned in the immediate area of the joint to assure good bonding of the sleeve; and (4) an innovative bolt-on entry fitting is required to conduct repair operations on live mains. The development effort is divided into eleven Tasks. Task 1 (Program Management) and Task 2 (Establishment of Detailed Design Specifications) were completed in prior quarters while Task 3 (Design and Fabricate Ratcheting Stainless-Steel Repair Sleeves) has progressed to installing prototype sleeves in cast-iron test pipe segments. Efforts in the current quarter continued to focus on Tasks 4-8. Highly valuable lessons were learned from field tests of the 4-inch gas pipe repair robot in cast-iron pipe at Public Service Electric & Gas. (These field tests were conducted and reported last quarter.) These tests identified several design issues which need to be implemented in both the small- and large-diameter repair robots for cast-iron pipe to assure their commercial success. For Task 4 (Design, Fabricate and Test Patch Setting Robotic Train), work has been directed on increasing the nitrogen bladder reservoir volume to allow at least two complete patch inflation/patch setting cycles in the event the sleeve does not set all ratchets in the same row on the first attempt. This problem was observed on a few of the repair sleeves that were recently installed during field tests with the small-diameter robotic system. For Task 5 (Design & Fabricate Pipe-Wall Cleaning Robot Train with Pan/Zoom/Tilt Camera), the recent field tests showed clearly that, in mains with low gas velocities, it will be necessary to improve the system's capacity to remove debris from the immediate vicinity of the bell and spigot joints. Otherwise, material removed by the cleaning flails (the flails were found to be very effective in cleaning bell and spigot joints) falls directly to the low side of the pipe and accumulates in a pile. This accumulation can prevent the sleeve from achieving a leak-free repair. Similarly, it is also deemed necessary to design an assembly to capture existing service-tap coupons and allow their removal from the inside of the pipe. These coupons were found to cause difficulty in launching and retrieving the small pipe repair robot; for example, one coupon lodged beneath the end of the guide shoe. Designs for new features to accomplish these goals for the large robotic system were pursued and are presented in this report. Task 6 (Design & Build Surface Control and Monitoring System) was previously completed with the control and computer display Functions being operated through LabVIEW. However, this must now be revisited to add control routines for the coupon catcher to be added. This will most likely include a lift-off/place-on magnet translation Function. Task 7 (Design & Fabricate Large Diameter Live Access System) progressed to completing the detailed design of the entry fitting for 12-inch diameter cast iron pipe in the previous quarter. Field tests with the 4-inch size fitting were completely successful and did not reveal any significant design issues. The primary suggestion from the PSE&G field crew was to produce a version which completely bolts together and does not require a long seam weld. This could be used in low-pressure cast iron mains to reduce installation time. A bolt-on version is being designed based on this recommendation. Task 8 (System Integration and Laboratory Validation) continued with the development of the robot module inter-connects and of a master LabVIEW-based system display and control software

Kiran M. Kothari - One of the best experts on this subject based on the ideXlab platform.

  • SEALING LARGE-DIAMETER CAST-IRON PIPE JOINTS UNDER LIVE CONDITIONS
    2005
    Co-Authors: Kiran M. Kothari, Gerard T. Pittard
    Abstract:

    Utilities in the U.S. operate over 75,000 km (47,000 miles) of old cast-iron pipes for gas distribution. The bell-and-spigot joints that connect pipe sections together tend to leak as these pipes age. Current repair practices are costly and highly disruptive. The objective of this program is to design, test and commercialize a robotic system capable of sealing multiple cast-iron bell and spigot joints from a single pipe entry point. The proposed system will perform repairs while the pipe remains in service by traveling through the pipe, cleaning each joint surface, and installing a stainless-steel sleeve lined with an epoxy-impregnated felt across the joint. This approach will save considerable time and labor, avoid traffic disruption, and eliminate any requirement to interrupt service to customers (which would result in enormous expense to utilities). Technical challenges include: (1) repair sleeves must compensate for diametric variation and eccentricity of old cast-iron pipes; (2) the assembly must travel long distances through pipes containing debris; (3) the pipe wall must be effectively cleaned in the immediate area of the joint to assure good bonding of the sleeve; and (4) an innovative bolt-on entry fitting is required to conduct repair operations on live mains. The development effort is divided into eleven Tasks. Task 1 (Program Management) and Task 2 (Establishment of Detailed Design Specifications) were completed previously. Task 3 (Design and Fabricate Ratcheting Stainless-Steel Repair Sleeves) has progressed to installing prototype sleeves in test cast-iron pipe segments. Efforts in the current quarter continued to be focused on Tasks 4-8. Highly valuable lessons were learned from field tests of the 4-inch gas pipe repair robot in cast-iron pipe at Public Service Electric & Gas. (These field tests were conducted and reported previously.) Several design issues were identified which need to be implemented in both the small- and large-diameter repair robots for cast-iron pipe to assure their commercial success. For Task 4 (Design, Fabricate and Test Patch Setting Robotic Train), previous problems with bladder design and elastomeric material expansion in the large mains were addressed. A new bladder based on a commercially available design was obtained and tested with success. Minor improvements were highlighted during patch-setting tests and are now being pursued. For Task 5 (Design and Fabricate Pipe-Wall Cleaning Robot Train with Pan/Zoom/Tilt Camera), the previous field tests showed clearly that, in mains with low gas velocities, it will be necessary to improve the system's capacity to remove debris from the immediate vicinity of the bell and spigot joints. Otherwise, material removed by the cleaning flails (the flails were found to be very effective in cleaning bell and spigot joints) falls directly to the low side of the pipe and accumulates in a pile. This accumulation can prevent the sleeve from achieving a leak-free repair. Similarly, it is also deemed necessary to design an assembly to capture existing servicetap coupons and allow their removal from the inside of the pipe. Task 6 (Design and Build Surface Control and Monitoring System) was previously completed with the control and computer display Functions being operated through LabVIEW. However, this must now be revisited to add control routines for the coupon catcher that will be added. This will most likely include a lift-off/place-on magnet translation Function. Task 7 (Design and Fabricate Large Diameter Live Access System) progressed to completing the detailed design for a bolt-on entry fitting for 12-inch diameter cast-iron pipe in the current quarter. The drilling assembly for cutting an access hole through the wall of the gas main was also designed, along with a plug assembly to allow removing all tools from the live main and setting a blind flange on the entry fitting prior to burial. These designs are described in detail in the report. Task 8 (System Integration and Laboratory Validation) continued with the development of the robot module inter-connects and of a master LabVIEW-based system display and control software

  • SEALING LARGE-DIAMETER CAST-IRON PIPE JOINTS UNDER LIVE CONDITIONS
    2005
    Co-Authors: Kiran M. Kothari, Gerard T. Pittard
    Abstract:

    Utilities in the U.S. operate over 75,000 km (47,000 miles) of old cast-iron pipes for gas distribution. The bell-and-spigot joints that connect pipe sections together tend to leak as these pipes age. Current repair practices are costly and highly disruptive. The objective of this program is to design, test and commercialize a robotic system capable of sealing multiple cast-iron bell and spigot joints from a single pipe entry point. The proposed system will perform repairs while the pipe remains in service by traveling through the pipe, cleaning each joint surface, and installing a stainless-steel sleeve lined with an epoxy-impregnated felt across the joint. This approach will save considerable time and labor, avoid traffic disruption, and eliminate any requirement to interrupt service to customers (which would result in enormous expense to utilities). Technical challenges include: (1) repair sleeves must compensate for diametric variation and eccentricity of cast-iron pipes; (2) the assembly must travel long distances through pipes containing debris; (3) the pipe wall must be effectively cleaned in the immediate area of the joint to assure good bonding of the sleeve; and (4) an innovative bolt-on entry fitting is required to conduct repair operations on live mains. The development effort is divided into eleven Tasks. Task 1 (Program Management) and Task 2 (Establishment of Detailed Design Specifications) were completed in prior quarters while Task 3 (Design and Fabricate Ratcheting Stainless-Steel Repair Sleeves) has progressed to installing prototype sleeves in cast-iron test pipe segments. Efforts in the current quarter continued to focus on Tasks 4-8. Highly valuable lessons were learned from field tests of the 4-inch gas pipe repair robot in cast-iron pipe at Public Service Electric & Gas. (These field tests were conducted and reported last quarter.) These tests identified several design issues which need to be implemented in both the small- and large-diameter repair robots for cast-iron pipe to assure their commercial success. For Task 4 (Design, Fabricate and Test Patch Setting Robotic Train), work has been directed on increasing the nitrogen bladder reservoir volume to allow at least two complete patch inflation/patch setting cycles in the event the sleeve does not set all ratchets in the same row on the first attempt. This problem was observed on a few of the repair sleeves that were recently installed during field tests with the small-diameter robotic system. For Task 5 (Design & Fabricate Pipe-Wall Cleaning Robot Train with Pan/Zoom/Tilt Camera), the recent field tests showed clearly that, in mains with low gas velocities, it will be necessary to improve the system's capacity to remove debris from the immediate vicinity of the bell and spigot joints. Otherwise, material removed by the cleaning flails (the flails were found to be very effective in cleaning bell and spigot joints) falls directly to the low side of the pipe and accumulates in a pile. This accumulation can prevent the sleeve from achieving a leak-free repair. Similarly, it is also deemed necessary to design an assembly to capture existing service-tap coupons and allow their removal from the inside of the pipe. These coupons were found to cause difficulty in launching and retrieving the small pipe repair robot; for example, one coupon lodged beneath the end of the guide shoe. Designs for new features to accomplish these goals for the large robotic system were pursued and are presented in this report. Task 6 (Design & Build Surface Control and Monitoring System) was previously completed with the control and computer display Functions being operated through LabVIEW. However, this must now be revisited to add control routines for the coupon catcher to be added. This will most likely include a lift-off/place-on magnet translation Function. Task 7 (Design & Fabricate Large Diameter Live Access System) progressed to completing the detailed design of the entry fitting for 12-inch diameter cast iron pipe in the previous quarter. Field tests with the 4-inch size fitting were completely successful and did not reveal any significant design issues. The primary suggestion from the PSE&G field crew was to produce a version which completely bolts together and does not require a long seam weld. This could be used in low-pressure cast iron mains to reduce installation time. A bolt-on version is being designed based on this recommendation. Task 8 (System Integration and Laboratory Validation) continued with the development of the robot module inter-connects and of a master LabVIEW-based system display and control software

Tom Chau - One of the best experts on this subject based on the ideXlab platform.

  • short term music training enhances verbal intelligence and executive Function
    Psychological Science, 2011
    Co-Authors: Sylvain Moreno, Ellen Bialystok, Raluca Barac, Glenn E Schellenberg, Nicholas J Cepeda, Tom Chau
    Abstract:

    Researchers have designed training methods that can be used to improve mental health and to test the efficacy of education programs. However, few studies have demonstrated broad transfer from such training to performance on untrained cognitive activities. Here we report the effects of two interactive computerized training programs developed for preschool children: one for music and one for visual art. After only 20 days of training, only children in the music group exhibited enhanced performance on a measure of verbal intelligence, with 90% of the sample showing this improvement. These improvements in verbal intelligence were positively correlated with changes in Functional brain plasticity during an executive-Function Task. Our findings demonstrate that transfer of a high-level cognitive skill is possible in early childhood.

Shoji Itakura - One of the best experts on this subject based on the ideXlab platform.

  • east west cultural differences in context sensitivity are evident in early childhood
    Developmental Science, 2013
    Co-Authors: Toshie Imada, Stephanie M Carlson, Shoji Itakura
    Abstract:

    Accumulating evidence suggests that North Americans tend to focus on central objects whereas East Asians tend to pay more attention to contextual information in a visual scene. Although it is generally believed that such culturally divergent attention tendencies develop through socialization, existing evidence largely depends on adult samples. Moreover, no past research has investigated the relation between context-sensitivity and other domains of cognitive development. The present study examined children in the United States and Japan (N = 175, age 4-9 years) to investigate the developmental pattern in context-sensitivity and its relation to executive Function. The study found that context-sensitivity increased with age across cultures. Nevertheless, Japanese children showed significantly greater context-sensitivity than American children. Also, context-sensitivity fully mediated the cultural difference in a set-shifting executive Function Task, which might help explain past findings that East Asian children outperformed their American counterparts on executive Function.

Annette Kasparek - One of the best experts on this subject based on the ideXlab platform.

  • cognitive modulation of midbrain Function Task induced reduction of the pupillary light reflex
    International Journal of Psychophysiology, 2000
    Co-Authors: Stuart R Steinhauer, Ruth Condray, Annette Kasparek
    Abstract:

    The activation of processing resources has widespread effects in the nervous system. A model of pupillary control systems (Steinhauer S.R. , Hakerem G., 1992. The pupillary response in cognitive psychophysiology and schizophrenia. Ann. N.Y. Acad. Sci. 658, 182-204) had predicted that ongoing cognitive activation should result in inhibition of the light reaction at the level of the oculomotor nucleus, n. III, in the midbrain. In this study, modification of parameters of the pupillary reaction to light were examined during varying Task demands. The averaged light reaction was recorded from 33 male and female healthy volunteers during the performance of a serial 7 subtraction Task and compared to a 'no Task' condition. For 13 subjects, an additional verbalization Task with little processing demand (add 1) also was presented. Two types of effects were observed. Firstly, the tonic pupil diameter increased from the no Task to the easy (add 1) Task, and increased further in the more demanding condition (subtract 7). Secondly, the extent of the phasic light reaction was significantly reduced and the latency at the end of the contraction was significantly decreased in the 'subtract 7' condition compared to both the no Task and easy conditions (which did not differ from each other). The locus of interference with the light reaction was the Edinger-Westphal complex of the oculomotor nucleus, which is the motor center for the pupillary sphincter muscles. Descending cortical influences inhibited the activity of the Edinger-Westphal complex. Thus, increasing activation had a tonic inhibitory effect on this center, while higher levels of processing complexity produced a separate component of inhibition that interacted with dynamic activation at this midbrain site. It was suggested that the variation in the light reaction is quantitatively responsive to varying processing loads, and may be utilized as a sensitive metric for a wide variety of cognitive operations.